Modernization of the traffic station Flensburg Implementation planning for the new construction of the PA system, preparation of the control technology for the passenger information system and generation of the tendering documents with performance specifications. Period: 2009-2010 |
Client DB Station & Service AG |
S-Bahn station Adlershof of S-Bahn Berlin GmbH Preparation of the implementation planning for the telecommunication installations for the new construction of the S-Bahn platform with system technologies like ELA, FIA, BMA, RIS, video dispatch systems and cable installations. Period: 2007-2010 |
Client S-Bahn Berlin GmbH, |
S-Bahn station Baumschulenweg of S-Bahn Berlin GmbH Preparation of the implementation planning for the telecommunication installations for the new construction of the S-Bahn platforms with system technologies like ELA, FIA, RIS, LON and cable installations. Period: 2007-2010 |
Client S-Bahn Berlin GmbH, |
New construction of a combined cycle power plant in Vlissingen, Planning, delivery, installation and commissioning of the information and safety systems. This included:
Period: 2007-2009 |
Client Kraftwerk Sloecentrale |
Modification of the S-Bahn junction Ostkreuz, Berlin Implementation planning for the modernization of the main junction buildings long-distance railway, ring line level and the platform Ro with commissioning of S-Bahn at Ro based on provisional constructions. Period: 2008-2009 |
Client DB Projektbau |
New construction of a steam power plant in Shuaibah, Saudi Arabia Planning, delivery, installation and commissioning of the information and safety systems. This included:
Period: 2007-2009 |
Client Kraftwerk Shuaibah |
NeiTech Allgäu, refurbishment of the route section Buchloe – Kaufbeuren Implementation planning in accordance with HOAI (performance phase 5) for the OWG cable connection with adaptation of the present GSM-R system equipment. The following systems were processed:
Period: 2007-2009 |
Client DB Station & Service AG |
New construction of the combined cycle power plant in Sumgait, Azerbaijan Planning, projecting and implementation work for equipping the power plant with a surveillance and communication system. Period: 2006-2009 |
Client Kraftwerk Sumgait |
New construction of a biomass power plant in Moerdijk, The Netherlands Planning, delivery, installation and commissioning of the information and safety systems. This included:
Period: 2007-2008 |
Client Kraftwerk Moerdijk |
New construction of a biomass power plant in Lockerbie, Great Britain Planning, delivery, installation and commissioning of the information and safety systems. This includes the telephone installation (backed by emergency power), as well as a video surveillance system with fixed and remote-controlled cameras. ISV also provides all replacement parts and warranty services. Period: 2007-2008 |
Client Kraftwerk Lockerbie |
Barrier-free expansion of the S-Bahn stop Heimeranplatz, Munich In the scope of the redesign and barrier-free expansion of the S-Bahn stop Heimeranplatz, ISV performed the implementation planning in acc. with HOAI (performance phase 5) for the telecommunication installations. This included the new construction and equipment of a distribution station for the central system technology (ELA) incl. power supply and cable connection installations, the installation of new loudspeaker equipment on the platform, relocation of the central PA system to the new distribution station as well as the adaptation, new installation and de-installation of route cabling and station cabling installations. Period: 2007-2008 |
Client DB Station & Service AG |
S-Bahn Berlin, BOS tunnel radio system Preparation of the implementation planning for the construction of a BOS tunnel radio system in the north-south tunnel of S-Bahn Berlin including involved systems like MAS90, BMA, SV. Period: 2007-2008 |
Client EADS |
IC workshop Berlin Rummelsburg I, centre hall Preparation of the implementation planning for the smoke and heat extraction installation. Period: 2007 |
Client DB Fernverkehr |
End-of-train detection installation Hörlkofe station Preparation of the implementation planning for TC installations, power engineering and traffic construction facilities for a video surveillance installation for end-of-train detection at Hörlkofen station. Period: 2007 |
Client DB Telematik |
New construction of a gas and steam power plant in Hamm-Uentrup, Planning, delivery, installation and commissioning of the information and safety systems. This includes an emergency power-backed telephone installation, a service-neutral data network based on OWG technology, a video surveillance system as well as an access control system with no-contact readers and PC-assisted administration. Period: 2006-2007 |
Client Siemens AG |
New construction ICE depot Leipzig Preparation of the implementation planning and invitation to tender for the fire alarm installations as well as the natural smoke and heat extraction facilities. Period: 2006-2007 |
Client DB Fernverkehr |
Power plant Inesko in Belgium Planning, delivery and commissioning of a video system (CCTV). Preparation of all installation documents as well as of a detailed documentation concerning the operation and maintenance of the facility. Period: 2006-2007 |
Client Siemens AG |
Power plant Cologne/Niehl Planning, delivery, installation and commissioning of the main communication installation type Stentofon. Preparation of all installation documents, drawings and user manuals as well as a detailed documentation for the operation and maintenance of the installation. Period: 2005-2006 |
Client Siemens AG |
Expansion of the metro "Metrorrey" in Monterrey, Mexico Planning and installation monitoring for the equipment of the underground railway with communication and surveillance systems as well as tunnel radio on connection with the expansion of the metro by one line. Period: 2004-2005 |
Client "Metrorrey" Monterrey |
New construction of the gas and steam power plant in Salta, Argentina Planning, projecting and implementation work for equipping the power plant with communication installations and a combined telephone and data network. Period: 2004-2005 |
Client Kraftwerk Salta |